Please note the following upcoming work around the exterior of the new Nicol Building:

  • Regrading and repaving of the existing lanes to the west and north of the site.
  • Removal and replacement of west sidewalk along Campus Ave.

The work will begin June 23-24 in the lane between the Architecture Building and Nicol Building and will progress clockwise around the site towards Minto Building and Campus Ave. The work is anticipated to take around 3 to 4 weeks to complete.

Impacts:

Access to the lane north of the site will be limited. The contractor will have a work plan to accommodate Emergency vehicles. The sidewalk will remain open for pedestrians.

Campus Ave will be reduced to one lane during the period they are rebuilding the side walk. Pedestrians will be redirected to the east sidewalk.

Facilities Management and Planning appreciate your understanding as we complete this work.