Skip to Content

Energy Retrofit Program

As part of our Sustainability Strategy Carleton University has partnered with Honeywell to work on a long term program to identify opportunities and implement initiatives designed to conserve energy and create sustainable solutions for our campus.

This comprehensive approach to facility upgrades and enhancements will improve the indoor environment, providing consistent lighting levels, better temperature control and reduced drafts. It is also expected to provide significant savings in utility costs through higher efficiency and reduce carbon emissions.

Wider to individual building renewal is Carleton’s Energy Master Plan. The plan outlines our goals and objectives for managing, conserving and reducing energy consumption, alongside costs and estimated savings for proposed measures, as applicable to the whole campus.

Current Program:

Dunton Tower

Work within Dunton Tower commenced in August 2018 and is expected to be completed by Fall 2019. The program will reduce utility costs, scheduled maintenance and provide an improvement in the working environment of the building.

Total expected annual utility and operational savings: $119,542.

Annual Savings:

Energy Conservation Measures:

Nesbitt Building

Work within the Nesbitt Building commenced in February 2018 and is expected to be completed by November 2018. The program will reduce utility costs, scheduled maintenance and provide an improvement in the working environment of the building.

Total expected annual utility and operational savings: $68,927.

Annual Savings:

Energy Conservation Measures:

Maintenance Building

Work for the Maintenance Building began in August 2018 and is expected to be completed by November 2018. The program will reduce operating costs, scheduled maintenance and provide improvement in the working environment of the building:

Total anticipated annual utility and operational savings: $15,145.

Annual Savings:

Energy Conservation Measures:

Work completed:

The Mackenzie Engineering Building

Work within the Mackenzie Engineering Building commenced in August 2016. The program will reduce utility costs, scheduled maintenance and provide for an improvement in the working environment of the building.

Total expected annual utility and operational savings: $143,209

Energy Conservation Measures:

Minto Case Building 

Work within the Minto Case Building commenced in August 2016 and was completed by May 2018. The program reduced utility costs, scheduled maintenance and provided an improvement in the working environment of the building.

Total anticipated annual cost savings: $101,454.00

Annual Savings:

Energy Conservation Measures:

Loeb Building

Work within the Loeb Building commenced in April 2015 and was complete by the end of October 2015. The program realized reduced utility costs, reduced scheduled maintenance and an improvement in the working environment of the building.

Total expected annual cost savings: $158,281

Energy Measures

Athletics Centre

The Athletics Centre was the second building selected in the program and allowed for greater investment and savings to be realized. This was completed in winter 2014.

Total expected annual cost savings: $137,409

Energy Measures

Robertson Hall

Robertson Hall was the first building to be selected as part of the energy retrofit program. The building’s lighting, mechanical systems and water systems were improved, and ultimately energy use reductions also led to cost savings. This was completed in summer 2014.

Total annual Cost Savings: $120,184

Annual Energy Savings:

Energy Measures