Project Schedule

River Site

TaskStart DateFinish Date
MobilizationAugust 2009
Excavation and foundationsAugust 2009December 2009
Slabs and columnsDecember 2009June 2010
Exterior worksFebruary 2010August 2010
Interior worksMay 2010May 2011
Exterior landscapingMay 2011August 2011
Commissioning and testingApril 2011August 2011
OccupancyAugust 2011

Canal Site

TaskStart DateFinish Date
MobilizationJune 2009
Excavation and foundationsJune 2009September 2009
Slabs and columnsSeptember 2009April 2010
Exterior worksNovember 2009November 2010
Interior worksFebruary 2010November 2010
Exterior landscapingAugust 2010November 2010
Commissioning and testingAugust 2010December 2010
OccupancyJanuary 2011